Fri, 01/24/2020 - 09:45
WANO Technical Support Mission ended up at Zaporizhzhia NPP

WANO Technical Support Mission on “Application of risk-informed approaches (risk-monitoring) for maintenance and repair optimization during power unit operation at power” took place at Zaporizhzhia NPP.

This project is implemented at Unit 2 with international technical assistance of USA Government. The primary objective is to increase the utilization factor of installed capacity by means of security important systems repair, during power unit operation at power and to reduce the duration of outages without security diminution.


Tue, 01/21/2020 - 08:50
WANO Technical Support Mission started at Zaporizhzhia NPP

WANO Technical Support Mission on “Application of risk-informed approaches (risk-monitoring) for maintenance and repair optimization during power unit operation at power” takes place on January 20-24, 2020 at Zaporizhzhia NPP.

The WANO experts were introduced, mission purposes and objectives and challenging issues, which are to be solved, were announced at the entrance meeting.


As of the time 04/08/2020 - 04:41

Performance indicators
Power Unit №1 985 MW
Power Unit №2 770 MW
Power Unit №3 -
Power Unit №4 871 MW
Power Unit №5 769 MW
Power Unit №6 -
Total plant load 3395 MW
Radiation conditions
Industrial ground 0.07 μSv/h
Energodar 0.08 μSv/h
Meteorological state
Air temperature 2.8
Wind SE
Wind speed 0.4 m/s
Relative humidity 57 %
Atmospheric pressure 773 mm Hg