Tue, 03/17/2020 - 09:20
Zaporizhzhia NPP Unit 2 there are 200 billion kWh of electricity!

Zaporizhzhia NPP Unit 2 has generated 200 billion kWh of electricity since the beginning of its operation.

"This milestone is a reflection of the stable work of the entire staff of the plant. Our main task is safe, reliable and efficient production of electricity, which we fulfil with strict observance of the requirements of Ukrainian and international rules, norms and standards on nuclear, radiation and environmental safety,” said Petro Kotin, General Manager of Zaporizhzhia NPP.


Fri, 01/24/2020 - 09:45
WANO Technical Support Mission ended up at Zaporizhzhia NPP

WANO Technical Support Mission on “Application of risk-informed approaches (risk-monitoring) for maintenance and repair optimization during power unit operation at power” took place at Zaporizhzhia NPP.

This project is implemented at Unit 2 with international technical assistance of USA Government. The primary objective is to increase the utilization factor of installed capacity by means of security important systems repair, during power unit operation at power and to reduce the duration of outages without security diminution.


Tue, 01/21/2020 - 08:50
WANO Technical Support Mission started at Zaporizhzhia NPP

WANO Technical Support Mission on “Application of risk-informed approaches (risk-monitoring) for maintenance and repair optimization during power unit operation at power” takes place on January 20-24, 2020 at Zaporizhzhia NPP.

The WANO experts were introduced, mission purposes and objectives and challenging issues, which are to be solved, were announced at the entrance meeting.


Wed, 12/04/2019 - 08:00
The specialists of Zaporizhzhia NPP were adopting the experience of the RiskWatcher users

The specialists of Zaporizhzhia NPP participated in the International RiskWatcher Users Conference held in London. The representatives of the countries - users of that software, including Japan, France, Slovakia, Hungary, USA, UK, - shared their experience, including Japan, France, Slovakia, Hungary, USA, UK.

At Zaporizhzhia NPP a project is being implemented to optimize the repair and maintenance of the systems for Unit 2. The purpose of the project is to perform maintenance of the equipment during operation of the power unit on power.


As of the time 11/29/2020 - 12:48

Performance indicators
Power Unit №1 961 MW
Power Unit №2 1018 MW
Power Unit №3 1020 MW
Power Unit №4 1007 MW
Power Unit №5 -
Power Unit №6 1025 MW
Total plant load 5031 MW
Radiation conditions
Industrial ground 0.08 μSv/h
Energodar 0.09 μSv/h
Meteorological state
Air temperature 8.3
Wind SE
Wind speed 4.5 m/s
Relative humidity 96 %
Atmospheric pressure 763 mm Hg